De-Shuttering time of different RCC Members
RCC Member
|
De-shuttering time
|
For columns, walls, vertical form works
|
16-24 hrs.
|
Soffit formwork to slabs
|
3 days (props to be refixed after removal)
|
Soffit to beams props
|
7 days (props to refixed after removal)
|
Beams spanning upto 4.5m
|
7 days
|
Beams spanning over 4.5m
|
14 days
|
Arches spanning up to 6m
|
14 days
|
Arches spanning over 6m
|
21 days
|