HARDCORE / SOLING UNDER FLOORS/FOUNDATIONS:



HARDCORE / SOLING UNDER FLOORS/FOUNDATIONS:



SCOPE

The work covered under this specification includes all type of soling work either by bricks or by rubble stones  laid  under  floors  /  foundations,  hand  packed,  complete  as  per  specification  mentioned  below and applicable drawings.


RUBBLE SOLE FLOORING

The rubble stone shall be of best variety of black trap / granite / basalt or other approved-variety of stone available locally. The stone shall be hard, durable free from defects and of required size and shall be approved by the Engineer-in-charge.


PREPARATION OF SURFACE

The bed on which rubble soling is to be laid shall be cleared of all loose materials, leveled, watered ad compacted and got approved by the Engineer-in-charge before laying rubble soling. Cable or pipe trenches if shown in the drawing and as required by the Engineer-in-charge shall be got done before the soling is started.


WORKMANSHIP

Over the prepared surface, the stone shall be set as closely as possible and well packed and firmly set. The stones shall be of full height and shall be laid so as to have their bases of the largest area resting on the sub-grade. Soling shall be laid in one layer of  230mm or 150mm depth or specified thickness of soling with a tolerance of 25mm.


After packing the stones properly in position, the interstices between them shall  be carefully filled with quarry spoils or stone chips of larger size possible to obtain a bard, compact surface. Spreading of loose spoils or stone chips is prohibited.


The entire surface shall be examined for any protrusions and the same shall be knocked off by a hammer and all interstices shall be filled with approved murrum. Excess murrum if any over the surfaces shall be removed. Unless otherwise specified, the murrum shall be supplied by the contractor at his own cost from the selected area.
The surfaces shall then be watered and consolidated  with  mechanical  or  sufficiently  heavy  wooden tampers  and  log-rammers  as approved by the Engineer.  After compaction, the Engineer-in-charge to give the required slope or level and dense sub-base and the surface shall present clean look. Adequate care shall be taken by the contractor while laying and compacting the rubble soling to see that concrete surfaces in contact with soling are not damaged.

MODE OF MEASUREMENT


The quoted rate shall be per square metre of the soling of specified thickness. The linear dimension shall be measured up to two places of decimals of a metre and are worked out correct to the two places of decimals of a square metre.   Plan areas of soling work actually done limiting to the dimensions as per drawings shall be measured for payment. The rate shall include all the materials labour, transport etc. and no extra payment shall be made for work done at different levels. The rate shall also include the cost of preparation of surface, all materials and labour, watering, consolidation etc. all complete.