Sunday, February 21, 2016

BACKFILLING IN SIDES OF FLOORS, PLINTH, UNDER FLOOR ETC..




BACKFILLING IN SIDES OF FLOORS, PLINTH, UNDER FLOOR ETC..

The backfilling shall be done after the concrete or masonry has fully set and shall be done in such a way as not to cause under-thrust on any part of the structure. Where suitable excavated material is to be used for backfilling, it shall be brought from the place where it was temporarily deposited and shall be used in backfilling. The scope of work for backfilling/ filling in foundation, plinth, under floors etc. shall include filling for all the buildings covered under the contract. Surplus earth available from one building, if required, shall be used for backfilling /filling for other buildings also within the specified lead mentioned in the item.
All timber  shoring and form work left  in  the  trenches, pits, floors etc.  shall be removed after their

necessity ceases and trash of any sort shall be cleared out from the excavation. All the space between foundation masonry or concrete and the sides of excavation shall be backfilled to the  original  surface  with  approved materials  in  layers  not  exceeding  150mm,  in  thickness, watered and well consolidated by means of rammers to at least 90% of the consolidation. Areas inaccessible to mechanical equipment such as areas adjacent to walls and columns etc. shall be tamped by hand rammer or by hand held power rammers to the required density. The backfill shall be uniform in character and free from large lumps, stones. shingle or boulder not larger than
75mm. in any direction, salt, clods, organic or other foreign materials which might rot. The backfilling in plinth and under floor shall be well consolidated by means of mechanical or hand operated rammers as specified to achieve the required density.
Test to establish proper consolidation as required will be carried out by the Department at rates specified. Two tests per 50 sqm. will be taken to ascertain the proper consolidation. The cost of tests carried out will be recovered from the contractor’s bill.


FILLING IN PLINTH AND UNDER FLOOR

After  the  available  suitable  excavated  materials  are  exhausted  as  backfilling,  the contractor shall notify the Engineer-in-charge of the fact and levels taken jointly with Engineer- in-charge. The earth, murrum, sand, gravel etc. or such materials suitable for filling proposed to be filled under floors and so mentioned in t he item of schedule of quantities shall then be brought to site from approved locations and sources.


EARTH FILLING

The earth, soft murrum etc. so brought shall be filled up in layers of 15 cm depth, each layer being well watered  and  consolidated  by approved  hand  or  mechanical  tampers  or  other suitable means to achieve the required density.


GRAVEL OR SAND FILLING

Gravel if required to be filled under floors, shall be single washed gravel of approved quality and of size varying from 12mm t0 20mm. it shall be uniformly blind with approved type of soil and / or sand to obtain full compaction. Gravel shall be filled in specified thickness and shall be well watered and rammed entirely to the satisfaction of the Engineer-in-charge.
If sand is required to be filled under floors, it shall be clean, medium grained and free from impurities. The filled in sand shall be kept  flooded with water for  24hrs. to  ensure maximum consolidation shall be done by the contractor at his own cost. The surface shall then be well dressed and got approved from Engineer-in-charge before any other work is taken over the fill.


LEAD AND LIFT

Lead: The lead for disposal / deposition of excavated materials shall be as specified in  the respective item of work. For the purpose of measurements of lead, the area to be excavated or filled or area on which excavated material is to be deposited/ disposed off shall be divided in suitable blocks and for each of the block, the distance between center lines shall be taken as the leads which shall be measured by the shortest straight line route on the plan and not the actual route adopted.


Lift: Lift shall be measured from ground level. Excavation up to 1.5m depth below ground level and depositing excavated material on the ground shall be included in the item of earthwork for various kinds of soil. Extra lift shall be measured in unit of 1.5m or part thereof. Obvious lift shall only be measured that is lifts inherent in the lead due to ground slope shall not be measured, except for lead up to 250m. All excavation shall be measured in  successive stages of 1.5m stating the commencing level. This shall not apply to cases where no lift is involved as in hill side cutting.


MODE OF MEASURTEMNTS

All excavation in areas having depth more than 30cm. pits, trenches etc. shall be measured net. The dimensions for the purpose of payment shall be reckoned on the horizontal area of the excavations for the purpose of payment shall be reckoned on the horizontal area of the excavation at the base for foundations of the walls, columns,    footings,  rafts  or  other  foundations,  multiplied  by the  mean  depth  from the  surface  of  ground determined by levels. Excavation for side slopes will not be paid for.  Excavation in areas having depths less than 30 cms. shall be measured as surface excavation on square meter basis, mentioning the average depth of excavation.


Reasonable working space beyond concrete dimension required for waterproofing  and shuttering where considered necessary in the opinion of Engineer-in-charge will be allowed in execution and considered for payment for underground water tank, sump septic tank etc.

Where direct measurements of rock excavation are not possible, volume of rock can be calculated on the basis of length, breadth, and depth of stacks made at site as mentioned in para 1.5.1 (c).  The net volume shall be worked out by reducing it by 40% taking the voids into consideration as 40%. Similarly to arrive at net quantity to be paid in the case of soil, reduction at 20% of corresponding stack / truck measurements shall be made.


The rate for excavation shall include carting and disposing and leveling the excavated materials within the specified lead. The rate shall also be inclusive of cost of all tools, plants, explosives, shoring, dewatering at various stages, labour, materials etc. to  complete all the operations specified.


The backfilling and consolidation in sides of foundation and in plinth with  excavated material will not be paid for separately. The rate quoted for excavation shall be deemed to have been included the cost of stacking of excavated materials, conveying within the specified lead, picking of selected stacked materials, conveying it to the place of final backfill, compaction to the required proctor density etc.


Payment for filling and consolidation inside the trenches, sides of foundations, plinth etc. with selected materials brought by the contractor other than the excavated material, shall be paid for separately as per the rates in schedule of quantities which includes cost  of such materials/ excavation, royalty, its conveyance within the specified lead, watering, consolidating, dressing etc.  Actual quantity of consolidated filling shall be measured and paid in cubic meters up to two places of decimal.


The rate quoted in cum. for items of excavation is deemed to include the necessary additional quantity of excavation involved beyond the plan dimensions of the work which may be necessary to be carried out for carrying out the work in an engineering made, decided upon by the contractor.  Therefore no extra payment will be made for any excavation done other than the required quantity as per the plan dimension indicated in the drawings.


Measurements for excavation over areas shall be determined by levels or by "Dead men" or both at the discretion of the Engineer-in-charge. If however the Engineer-in-charge decided on measurement by levels, levels of site shall be jointly taken and recorded by the Engineer-in- charge or his representatives and the contractor, before commencement of the work and after completion of the work and the quantity of work done shall be computed based on these levels. The volume of earth work shall be computed based on "Simpson's formula  ' or any other approved method at the discretion of the Engineer-in-charge.